State bid reference · TN
Tennessee: ARAP water alterations are a separate construction input
TDEC identifies aquatic-resource authorization for physical alterations to streams, rivers, lakes or wetlands, including road/utility crossings, bank work, relocation and structural fill. Federal authorization may also be relevant.
Sitework Estimate provides remote, plan-based quantity takeoff support. This page does not establish a local office, completed local project, engineering approval or permit coverage.
What this changes in the bid review
Estimating interpretation: An erosion-control permit does not describe the full construction scope of a stream crossing. Quantify the accepted crossing and temporary measures from their own drawings rather than using a generic pipe-trench allowance.
Check the project documents
Clarification to request: Which aquatic-resource authorization governs the crossing, temporary diversion and final restoration?
0 of 3 checks reviewed. Notes stay in this tab; download to keep a copy.
Official context
Tennessee Aquatic Resource Alteration Permit
Source checked . Confirm the current incorporated edition and project approval with the named authority. The checks above are our estimating interpretation; the linked agency supplies the source context.
Local bid references with agency sources
- Shelby: Memphis and Shelby County manual coordination
- Davidson: Grading, residential infill and as-built review routes
- Knox: Knoxville city site-development review within Knox County
- Hamilton: Multi-jurisdictional water-quality program and runoff permits
These references address the named jurisdiction. Other municipalities can use different criteria and approval routes.